Rominserv (September 2010)
Scope of Work
- Project Management
- Planning activities
- Procurement services and warehousing
- Dismantling of the existing Reactor (approx. 220t), steel structure and piping
- Installation of a new Reactor (approx. 240t)
- Electrical an Instrumentation works
- Construction of new foundation and refractory lining works
- Scaffolding, insulation and painting works
- Cranes
- Commissioning and Start-up
- Technical documentation
Spotlights
- Short implementation time (30 days)
- 100,000 working hours without accidents
Location: Petromidia refinery, Romania