(07/2020)
Full replacement of the 120R2 reactor at Ploiesti, with expert heavy lift coordination and mechanical installation to plant specification. Completed within the shutdown window to the highest safety standard.
Scope:
- Engineering activities
- Prefabrication of materials
- Dismantling works
- Mechanical, Civil, E&I, and Scaffolding works
- Painting, NDT services
- Commissioning & start-up
Highlights:
- Execution during the turnaround (10 days)
- Heavy lift coordinated precisely
- Full compliance with refinery standards
- Reactor reinstated within shutdown window