OMV Petrom SA (2010)
Scope of work
Static works: 15 Columns, 34 Heat Exchanger, 37 Vessels, 1 Reactor,
Dynamic works: 3 Centrifugal Compressors, 10 Piston Compressors, 5 Steam Turbines, 3 Piston Pumps, 5 Centrifugal Pumps (single stage), 2 Centrifugal Pumps (multistage pumps)
Spotlights
Only 1 month for planning of the TAR
25 working days only
Working hours: approx. 100.000
Accidents: 0