OMV Schwechat (2006-2007)
Scope of delivery and service
- Delivery of ca. 3200 t of components (reactors, steel construction and enclosures, sewers with halar-coating, blowers, e-filters etc.)
- Assembly of ca. 7,500 t of components (entire plant)
- Delivery and assembly of 380 t piping systems including hanging and supports, C-nozzle, rust-free, coated, etc.
- Integration of the new plant into the existing power plant
Highlight
- Spatial conditions and schedule (delayed deliveries, extensions of project scope, re-plannings…)
- Biggest project implemented by Christof Industries (600,000 hours of assembly, at peak times 320 fitters at the construction site)
Ort: Schwechat (Austria)