(07/2019 - 08/2019)
Scope:
- Replacement of centre pipes in reactors R21, R22, R23 and R24 within the DREFC Unit
- Pre-work planning, scaffolding and coordination of mechanical, electrical, instrumentation and civil activities
- Dismantling of existing bolts, nuts, pipes, covers and blind flanges
Removal of existing reactor centre pipes and transportation to the designated location
Installation of new centre pipes in reactors R21-R24
Reassembly of associated piping, covers, instruments and related components
Mechanical completion support and preparation for unit restart following the shutdown
Highlights:
- Successful replacement of centre pipes in four reactors during a critical refinery shutdown
- Complete execution within a 14-day shutdown window
- Coordinated multidisciplinary activities involving mechanical, electrical, instrumentation and civil works
- Safe removal and installation of critical reactor internals under tight schedule constraints
- Timely completion supporting the planned restart of the DREFC Unit