(05/2018)
- Rebuild of 4 coating sections
- Exchange of IR-drying equipment
- Delivery and Installation of gas and small bore piping
- Detail Engineering, delivery and Installation of duct for machine air system
Highlights:
- Execution of the rebuild in 2 steps (2 days + 4 days)
- At the peak, 135 fitters were working at the standstill
- Assembly completion was 24 hours before the contractual penalty date
Location: Gratkorn, Austria