(2021-2023)
Mechanical rebuild and installation of Paper Machine PM4 at the Eilenburg mill, with OEM tolerances achieved and rebuild duration minimised for smooth, on-time handover to production.
PROJECT SCOPE
- PM4 paper machine rebuilt at Eilenburg
- Mechanical works and installation completed
- OEM tolerances achieved
SCOPE HIGHLIGHTS
- Rebuild duration minimised
- On-time handover to production