(01/2015 - 12/2016)
Scope:
- fabrication and erection of steel structure (approx. 70to);
- pipe connections above ground (supply materials, fabrication and erection (including
pressure test) for the pipe connections; NDT and PWHT related to the pipe connections;
anticorrosive protection; - underground piping (Supply materials, fabrication and erection (including pressure test) for
the carbon steel underground pipe connections; NDT and PWHT related to the pipe
connections, wrapping of the underground piping; - installation of static & rotating equipment, EI&C and substation container.
Highlights:
- Working-hours: ~ 35,000 h