(2017)
Based on a facility matrix, our customer was looking for a partner who could deliver the facility in a turnkey solution. The challenge was also that the facility should be designed for an easy upgrade. Christof Systems and the customer chose the modularised system together because it was compact, could mostly be manufactured in Austria, and the commissioning could be done before delivery to the construction site.
Task
Development, manufacturing, assembly, commissioning and erection on site of a solution for adding chilled water, compressed air and electrical supply to the test facility.
Particular challenges
The system had to be able to adduce the exact temperature control of +/- 1 Kelvin and the exact pressure control of +/- 0.2 bar. A big challenge was the high dynamic cooling power and electrical power requirements. Additionally, there was enormous time pressure to complete the project.
Scope of work
The container solution was fully developed in-house (basic and detail engineering as well as software development), manufactured in our workshop area (electrical and mechanical), assembled and commissioned based 100% on the customer requirements. The manufacturing
and the erection on site were done on time and the customer was able to operate the system as planned.
Further projects for modularised systems:
- Solutions for new Test Centres in the Automotive Industry
- Containerised solar power solution for self-power supply
- Containerised environment analysing and testing equipment