Mondi Packaging
Scope of Work
- replacement of the entire machine drive
- replacement of the gears in the gear boxes
- replacement of the entire recirculating oil lubrication system
- replacement of the Clupak-cylinder
Rebuild/new Installation of the Steam and Condensate System of PM 6 and PM 8
- rebuild/new installation of the complete steam and condensate system of the drier section of the PM 8
- installation of the measure and control system as well as the impulse pipes
- dismantling and new installation of the steam joints of the PM 6
- installation of the measure and control system and the impulse pipes
Revision of PM 6 and PM 7
- refurbishment of the HP hoods 1 and 2
- manufacture and installation of new brackets
- adjustment and replacement of the pneumatic adjusting cylinders
- check and replacement of cardan joints at the drives of wet section and drier section
Boiler Revision
- revision of the bark boiler
- revision of the electric filter at CK II, CK III, the bark boiler and the lime kiln
- revision of the evaporation plant
- revision of CK II and CK III
Location: Frantschach (Austria)