(01/2019 – 08/2019)
Scope
- Mechanical installation works for PM8 and SM8 production lines
- Installation of ventilation and waste heat recovery systems for PM8 and SM8
- Installation and integration of RSM2 systems
- Support services during the electrical installation phase with a workforce of approximately 40 electricians
Highlights:
- Successfully mitigated delivery delays through additional shifts and rapid deployment of supplementary personnel, reaching a peak workforce of 150 specialists
- Implementation of a fully electronic material tracking system based on a newly developed database platform
- Effective management of complex, multidisciplinary installation activities across multiple project areas
- Flexible resource planning and workforce mobilisation to maintain project schedule targets
- Seamless coordination between mechanical and electrical installation teams
- Strong focus on safety, quality and efficient project execution throughout all phases of construction and installation activities
Location: Kehl, Germany