(07/2018 – 03/2019)
Scope:
- Mechanical and electrical erection of the laminar cooling system and water treatment plant
- Installation and integration of the thick plate cooling bed
- Erection of the finishing mill run-out table
- Complete plant cabling and electrical installation works
- Mechanical and electrical assembly of critical rolling mill infrastructure
Highlights:
- Successful execution within a highly demanding and compressed project schedule
- Co-ordinated mechanical and electrical installation activities across multiple plant areas
- Efficient management of interfaces between equipment installation, cabling and commissioning activities
- Delivery of key cooling and water treatment systems essential for plant performance and product quality
- Strong focus on safety, quality and adherence to project milestones
- Flexible resource planning and execution to meet tight programme requirements
- Seamless integration of new systems into the overall production process and plant infrastructure
Location: Frederiksvaerk, Denmark