(05/2017 – 08/2018)
- Cable trays (main ways and sub ways) – 16,400 m
- Cable pulling (electrical installation incl. earthing) – 165,500 m
- Cable connection – 16,000 pcs.
- Equipment installation (signal towers, scanners, transmitters) – 2,100 pcs.
- Equipotential bonding – 15,000 m
Highlights:
- 13,500 m of conveyor system – 4 stingray shuttle with 66 levels – network cabling – low voltage main distribution cabling planning
- Project Documentation in Polish language
Location: Gardno, Poland