(04/2018 – 07/2019)
- Electrical installation, modernisation of gas turbine
- Cable trays / cable pulling – 500 m / 34,500 m
- Cable connection / equipment installation – 11,000 pcs. / 300 pcs.
- Equipotential bonding – 1,000 m
Highlights:
- High safety requirements by end customer
- Provision of personnel for customer for commissioning work
- Extra efforts for updating the clients data system
- 5 of 10 customer´s health and safety awards went to Christof Industries
Location: Norfolk, Great Britain