VERBUND Thermal Power GmbH & Co KG (2012)
Scope:
- Replacement of five tube levels manufactured from 15Mo3 material (38 × 3.6 mm)
- Complete disassembly and reassembly of armouring as part of the tube replacement works
- Execution of heating surface pipe replacement within an operational industrial environment
- Welding, inspection and quality control of all replaced components
- Restoration of system integrity and operational readiness following completion of works
Highlights:
- Successful completion of all works within an exceptionally tight 12-day shutdown window
- Replacement of 710 heating surface pipes involving more than 2,200 weld seams
- Execution of complex multi-layer assembly activities requiring precise planning and co-ordination
- Efficient delivery under significant time pressure while maintaining quality and safety standards
- Successful management of highly restricted access and limited working space at both insertion and outlet points
- Challenging installation activities performed within confined areas of the combustion chamber
- Strong focus on workmanship, safety and schedule adherence throughout the shutdown period
- Reliable project execution ensuring timely return of the plant to operation
Ort: Mellach (Austria)