Manner Josef & Comp AG (2016-2017)
Tasking
Disassembly of a complete chocolate production factory (main production line) to replace the floor, subsequent modernisation of some plant components as well as reconstruction and commissioning of the plant within six weeks.
Challenges
The project required extensive planning, because there were no plans or descriptions of the plant available.
Achievement
25 employees spent around one year preparing the disassembly and re-assembly of the plant, which is made up of three industrial kitchens, because of the need to have a clear picture of the plant’s functionality before work could begin. Working in close cooperation with our customer, we were able to refresh and modernise the entire plant within the set timeframes.
Location: Wolkersdorf, Austria